The following
informational listing is a guideline of requirements to obtain a
building permit for commercial projects. Please be advised that
while we have made this list as comprehensive as possible, there
may be modifications specific to your project. In order to clarify
some of the terminology, please be aware of the following:
*“Construction
Supervisor License” The Massachusetts State Building Code
requires that a Construction Supervisor Licensee be responsible
to supervise the construction, reconstruction, alteration, repair,
removal or demolition involving any activity regulated by any
provision of the Building Code
When is a
building permit required?
Building Permits
are regulated by the Massachusetts State Building Code (780 CMR),
which states: “It shall be unlawful to construct, reconstruct,
alter, repair, remove or demolish a building or structure; or to
change the use or occupancy of a building or structure; to install
or alter any equipment for which provision is made or the
installation of which is regulated by 780 CMR without first filing
a written application with the building official and obtaining the
required permit therefor.”
How long does
it take to obtain a building permit?
Once all of the
required documents are submitted, the building official has
30 days to review and issue a permit or return for more
information. The goal of the Tewksbury Building Department is to
issue commercial permits within 14 days of a complete package
being submitted.
When are special permits
required from the Planning Board or Board of Appeals?
A special permit is required from the Planning Board
for non-residential developments meeting any of the following
criteria:
-
New building over 10,000 SF.
-
Addition over 5,000 SF.
-
Development that generates 500 or more daily vehicular
trips.
A site
plan special permit is required from the Planning Board
for any “externally enlarged” increase in excess of 240 SF of
floor area or any expansion of the ground area devoted to the use.
Some uses require special permits from the Zoning Board of
Appeals.
Applicants are urged to consult with the Building Commissioner in
order to insure that the proper permits are applied for.
What is required upon completion of the project?
The permit card
must be returned with the appropriate inspector’s and departments
signed off. Include a copy of the elevator certificate, if
applicable. Completion affidavits from the Architect and
Engineers, if applicable. All conditions included in any special
permits must be completed or bonding arrangements will be
necessary.
New Commercial Building
Complete
Building Permit Application
Community Check List: Assessor
(address)
Board of
Health – Septic
Board of
Health - Kitchen
DPW -
Sewer
DPW –
Water
Fire
Department
Planning
Conservation
Construction Supervisor License
Insurance Affidavit
Trash Disposal Form
3 sets Stamped Plans
Energy Code Review
AAB Compliance
Building Code Review
Control Construction
Affidavit
(Architects & Engineers)
Independent Structural Review
(check for requirement)
Copies of Recorded Special Permits
(if applicable)
Planning – site
Planning – use
Appeals – use
Appeals – variances
Copy of Planning Board Approved Site Plan -
(if applicable)
|
Commercial Addition
Complete Building
Permit Application
Community Check List:
Board of
Health – Septic
Board of Health - Kitchen
DPW -
Sewer
DPW –
Water
Fire
Department
Planning
Conservation
Construction Supervisor License
Insurance Affidavit
Trash Disposal Form
3 sets Stamped Plans
Commercial Energy
Code Review
AAB Compliance
Building Code Review
Chapter 34 Review
Control Construction
Affidavit
(Architects & Engineers)
Independent Structural Review
(check for requirement)
Copies of Recorded Special Permits
(if applicable)
Planning – site
Planning – use
Appeals – use
Appeals – variances
Copy of Planning Board Approved Site Plan
(if applicable)
|
Interior Tenant Fit-up
Complete
Building Permit Application
Community Check List:
Board of
Health - Kitchen
Fire
Department
Construction Supervisor License
Insurance Affidavit
Trash Disposal Form
3 sets Construction Plans – Stamped
Commercial Energy
Code Review
AAB Compliance
Building Code Review
Chapter 34 Review
Control Construction
Affidavit
(Architects & Engineers)
Copies of Recorded Special Permits
(if applicable)
Planning – site
Planning – use
Appeals – use
Appeals – variances
Copy of Planning Board Approved
Site Plan (if applicable)
|