Phase 6
Design Summary
Approximately 290 homes/businesses served
Approximately 23,000 LF (4.3 miles) of gravity sewer
1 Pumping Station (Hill Street and Main Street)
Approximately 1,400 LF of force main
Approximately 6 Grinder Pumps
Approximately 3,400 LF of water main replacement (bid alternate)
Environmental Impact Report (EIR) waiver granted
No ConCom approvals necessary
Phase 6 Schedule (2003)
Advertise Bids
April 4
Plans available to contractors
April 8
Bids received and opened
April 29
Recommendation to Award
May 9
Execute Construction Agreement May 27
Pre-Construction Conference
June 4
Public Information Meeting
June 19 7:30pm @ TMHS Aud.
Mobilize/Begin Construction
June 23
Phase 6 has been
completed.
The Hill St. pumping station is
up and running. 284 properties can
now connect to the Town's sewer system. Some of the streets received
final paving in 2004; the balance will be done in 2005.