Phase 7 Project Summary
Four Construction contracts
Approximately 119,000 LF (22.6 miles) of gravity sewer
8 pumping stations
Approximately 10,000 LF of force main
EIR approval required for construction
ConCom, DEP (WQC), Army Corps of Engineers approvals required for
construction.
Phase
7 Schedule
Field Survey
March to Oct 2003
Design Contract #22
May to Dec 2003
Design Contract #24
Aug 2003 to Jan 2004
Design Contract #23
Oct 2003 to April 2004
Design Contract #25
Nov 2003 to May 2004
Bidding Contract #22
Jan to March 2004
Bidding Contract #24
Feb to April 2004
Bidding Contract #23
May to July 2004
Bidding Contract #25
Jun to Aug 2004
Phase 7 Contract 22 Schedule (2004)
Advertise Bids
January 29
Plans available to contractors
Bids received and opened
February 26
Recommendation to Award
March
Execute Construction Agreement April
Pre-Construction Conference
May 20
Public Information Meeting
May 19 7:00pm @ TMHS Aud.
Mobilize/Begin Construction
June 1
Phase 7 Contract 24 Schedule:
Job advertised April 2,
2004
Bid opening April 29, 2004
Recommendation to Award
May
Execute Construction Agreement May
Pre-Construction Conference
May 20
Public Information Meeting
May 19 7:00pm @ TMHS Aud.
Mobilize/Begin Construction
June 15
Phase 7 Contract 23 Schedule:
Job advertised
June
Bid opening
July 22
Recommendation to Award
August
Execute Construction Agreement
Pre-Construction Conference
Public Information Meeting
Oct 12 7:30 @ TMHS Aud.
Mobilize/Begin Construction
Mid October
Phase 7 Contract 25 Schedule:
Job advertised
June
Bid opening
July 29
Recommendation to Award
August
Execute Construction Agreement
Pre-Construction Conference
Public Information Meeting
Oct 12 7:30 @ TMHS Aud.
Mobilize/Begin Construction
Mid November
Phase 7 has been
completed. All pumping stations
are
up and running. Over 1,300 properties can
now connect to the Town's sewer system. Some of the streets received
final paving in 2005 and 2006; the balance will be done in 2007.