Phase 8 (Contracts
26, 27, and 28)
as of
September 18, 2007
All contracts 26 and 27 in
Phase 8 have been turned over to the Town. If you live in this area
you should have received a letter telling you that you can now
connect to the system.
Contract 28 is scheduled to be completed during
2007.
Phase 8 streets by contract
This list breaks out Phase 8 into the
three contracts that will be used for construction. The contract
numbers are 26, 27, and 28.
Phase 8 maps
Contract 26
Contract 27
Contract 28
Phase 8 Project Summary
Three Construction contracts
Approximately 89,000 LF (16.9 miles) of gravity sewer
7 pumping stations
Approximately 7,200 LF of force main
ConCom, DEP (WQC), Army Corps of Engineers approvals required for
construction.
Phase
8 Schedule
Field Survey
Design Contract #26 Mar 2004 - Jan 2005
Design Contract #27
April 2004 - Feb 2005
Design Contract #28 May 2004 - Feb 2006
Bidding Contract #26 Feb 2005
- April 2005
Bidding Contract #27 Mar 2005 - May 2005
Bidding Contract #28 March 2006 - May 2006
Phase 8 Contract 26 Schedule:
Advertise Bids
Plans available to contractors
Bids received and opened
Recommendation to Award
Execute Construction Agreement
Pre-Construction Conference
Public Information Meeting
Mobilize/Begin Construction
.
Phase 8 Contract 27 Schedule:
Advertise Bids
Plans available to contractors
Bids received and opened
Recommendation to Award
Execute Construction Agreement
Pre-Construction Conference
Public Information Meeting
Mobilize/Begin Construction
Phase 8 Contract 28 Schedule:
Advertise Bids
Plans available to contractors
March 27, 2006
Bids received and opened April
20, 2006
Recommendation to Award
Execute Construction Agreement
Pre-Construction Conference
Public Information Meeting
Mobilize/Begin Construction