Phase 9 (Contracts
29, 30, and 31)
as of
September 18, 2007
Phase 9 streets by contract
This list breaks out Phase 9 into the
three contracts that will be used for construction. The contract
numbers are 29, 30, and 31.
Phase 9 map
Public Meeting for Contracts 30 and 31
Phase 9 Project Summary
Three Construction contracts
Approximately 88,000 LF (16.7 miles) of gravity sewer
3 pumping stations
Approximately 48,000 LF of force main
ConCom, DEP (WQC), Army Corps of Engineers approvals required for
construction.
Phase
9 Schedule
Field Survey
Design Contract #29 April 2005 - February 2006
Design Contract #30
July 2005 - April 2006
Design Contract #31 Oct 2005 - July 2006
Bidding Contract #29 March 2006
- May 2006
Bidding Contract #30 Jay 2006 - July 2006
Bidding Contract #31 Aug 2006 - Oct 2006
Phase 9 Contract 29 Schedule:
Advertise Bids
Plans available to contractors April
3, 2006
Bids received and opened April
27, 2006
Recommendation to Award
Execute Construction Agreement
Pre-Construction Conference
Public Information Meeting
Mobilize/Begin Construction
.
Phase 9 Contract 30 Schedule:
Advertise Bids
Plans available to contractors
Bids received and opened
Recommendation to Award
Execute Construction Agreement
Pre-Construction Conference
Public Information Meeting
November 28, 2006
Mobilize/Begin Construction
.
Phase 9 Contract 31 Schedule:
Advertise Bids
Plans available to contractors
Bids received and opened
February 22, 2007
Recommendation to Award
March 2007
Execute Construction Agreement
Pre-Construction Conference
Public Information Meeting
November 28, 2006
Mobilize/Begin Construction