Phase 11 streets by contract
This list breaks out Phase 11 into the
three contracts that will be used for construction. The contract
numbers are 34, 35, and 36.
Phase 11 map
Phase 11 Project Summary
Three Construction contracts
Approximately xx,000 LF (xx miles) of gravity sewer
x pumping stations
Approximately x,000 LF of force main
ConCom, DEP (WQC), Army Corps of Engineers approvals required for
construction.
Phase
11 Schedule
Field Survey
Design Contract #34
Design Contract #35
Design Contract #36
Bidding Contract #34
Bidding Contract #35
Bidding Contract #36
Phase 11 Contract 34 Schedule:
Advertise Bids
Plans available to contractors
Bids received and opened
Recommendation to Award
Execute Construction Agreement
Pre-Construction Conference
Public Information Meeting
Mobilize/Begin Construction
.
Phase 11 Contract 35 Schedule:
Advertise Bids
Plans available to contractors
Bids received and opened
Recommendation to Award
Execute Construction Agreement
Pre-Construction Conference
Public Information Meeting
Mobilize/Begin Construction
Phase 11 Contract 36 Schedule:
Advertise Bids
Plans available to contractors
Bids received and opened
Recommendation to Award
Execute Construction Agreement
Pre-Construction Conference
Public Information Meeting
Mobilize/Begin Construction