TEWKSBURY SIDEWALK
CONSTRUCTION SCHEDULE |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Unit |
|
|
|
|
|
Priority |
Street
Name |
Limit
Description |
Sewer
Construction |
Tentative
Sewer |
Sidewalk
Design |
Anticipated |
Approxlmata |
Treatment |
Costs($} |
Estimated |
Budgetary Cost
with |
|
|
|
# |
|
|
Completion
Date |
Contract
# |
Completion |
Construction
Period |
Length
(feet) |
Sidewalk &
berm |
Per
LF |
Construction Cost
($) |
Eng/Cont.
($) |
|
|
|
1 |
North
Street |
East to
RxR |
Summer
04 |
- |
Spring
2004 |
completed |
3100 |
SW+B |
70.00 |
217,000 |
217,000 |
|
|
|
2 |
North
Street |
RxR to
Andover (exl. state ROW area) |
Fall
04 |
- |
Spring
2005 |
Summer
2005 |
7400 |
SW+B |
35.00 |
259,000 |
284,900 |
|
|
|
3 |
Shawsheen
Street |
Bridge to
Ballard |
Fall
05-Spring 06 |
7/22 |
Spring
2004 |
Summer
2006 |
6100 |
SW+B |
30.00 |
183,000 |
183,000 |
|
|
|
4 |
Bridge
Street |
Shawsheen to
Gieger |
Fall
O5-Spring O6 |
7/22 |
Spring
2006 |
Summer
2006 |
1100 |
SW+B |
40.00 |
44,000 |
48,400 |
|
|
|
5 |
Brown/South |
Illinois to
Walgreen’s |
Spring
05 |
- |
Spring
2007 |
Summer
2007 |
3600 |
SW+B |
30.00 |
108,000 |
118,800 |
|
|
|
6 |
South
Street |
Pringle to
Gieger |
2006-Spring
07 |
7/24 |
Spring
2007 |
Summer
2007 |
3200 |
SW+B |
30.00 |
96,000 |
105,600 |
|
|
|
7 |
Shawsheen
Street |
Ballard to
East |
2006-Soring
07 |
7/23 |
Spring
2004 |
Summer
2008 |
5000 |
SW+B |
30.00 |
150,000 |
150,000 |
|
|
|
|
|
. |
|
|
|
|
|
|
|
|
|
|
|
|
8 |
Shawsheen
Street |
Main to
Bridge |
200S-Spring
07 |
7/25 |
Spring
2004 |
Summer
2008 |
2300 |
SW+B |
30.00 |
69,000 |
75,900 |
|
|
|
9 |
North
Street |
near state
ROW |
Summer 07
-Spring 08 |
8/28 |
Spring
2009 |
Summer
2009 |
2300 |
SW+B |
40.00 |
92,000 |
101,200 |
|
|
|
10 |
| | |